Skip to content
A trenchless crossing site alongside a railway line, the drilling rig set back from the track

Network Rail UTX guide

Network Rail undertrack crossings, stage by stage

A pipe, duct or cable taken under a railway is an undertrack crossing, a UTX, and it goes through a fixed sequence with Network Rail before the drill turns, then the works themselves with the track watched throughout, then a set of records. This guide walks through every stage in order. What each submission is for, what goes into it, where the site information goes in (the boreholes, the utility search, the track and topographical surveys), what we need from you at each point, and what you hold at the end. It is written for whoever has to programme and pay for the crossing, and it assumes you have never done one.

How the process fits together

A crossing under the railway is third-party work on an operating line, so Network Rail control it more closely than a road crossing. Two of their standards work together. NR/L2/CIV/044 is the technical rulebook for undertrack crossings, where the crossing sits, how deep, how it is built, how ground movement is controlled and how the track is monitored. NR/L2/CIV/003 is the engineering assurance standard, the approval in principle and the design and check certificates the design has to pass through. Around both sits an asset protection agreement between Network Rail and the party the crossing is for, which we call the scheme owner in this guide (the client, or the utility whose service it is). The scheme owner is the applicant. We provide the design package, commission the independent check, and install the crossing.

One thing to hold onto all the way through. Network Rail review and accept. They do not design, and they do not check. The design and the independent check are both provided by the applicant’s side, which in practice means us, and Network Rail confirm the assurance is in place and accept the result. That is why the roles and the checker are sorted out first, before anything is submitted.

If you have read our CD 622 guide for a National Highways road, six things are different under a railway. The ground investigation is required, not a decision. The depth is set by a 5mm limit on track movement, not by a cover figure. The independent check is done by a separate company. There is an agreement the scheme owner signs. The monitoring is of the track itself, with trains running over it. And the approvals are certificates on Network Rail’s forms rather than a chain of certified reports. If you want the short version and a price, the Network Rail UTX page is the place. This is the long version.

At a glance

The stages, what they contain, and what we need from you

StageWhat it containsWhere the site information goesWhat we need from you
0 Before the first submissionNetwork Rail Asset Protection engaged, the asset protection agreement, the wayleave applied for, the roles named, the independent checker acceptedThe utility records search starts nowWhere the crossing is, what is going in it, who the scheme owner is, the land either side of the railway, your dates
1 Approval in Principle (FORMA)Site constraints, the desk study, the utility records, the method and why, the alignment, preliminary calculations and drawings, the risk assessment, the contingency planUtility records, any existing ground investigation, any survey you already holdSign-off on the line and what is going in, anything you hold, the wayleave application in, the agreement, your say-so on the checker
2 Ground investigation and the baseline surveyBoreholes each side of the railway with laboratory testing, the track baseline and dilapidation survey, the topographical survey, the monitoring targets setThe boreholes and test results, the topographical survey, the track baselineLand access for the borehole rig, your decision on any investigation beyond the minimum, the track survey arranged through Asset Protection
3 The designThe ground model, the ground investigation and design reports, the settlement, heave and pipe loading calculations, the drawings, the track monitoring plan, the risk assessmentThe utility survey, the calculations, the drawings, the monitoring planFinal pipe or duct requirements, agreed pit positions, answers to anything Network Rail direct at the scheme owner
4 The independent check and the certificate (FORMB)The Category 3 check by a separate company, the design and check certificate for the crossing, a temporary works certificate where the pits need oneEverything above, certifiedNothing new usually
5 Before siteMethod statements to Network Rail at least 20 working days ahead, the monitoring plans accepted, construction drawings, contingency and emergency plans, any possession bookedNothing new, the paperwork is finalisedThe agreement in force, the wayleave granted, a named contact for the readings, any possession booked
6 The works, with the track monitoredBaseline readings, monitoring on the approach, the pilot bore accepted before reaming, the track read against the trigger levels, spoil and fluid reconciled every shiftEvery reading, the drilling records, the as-builtSite access, the named contact available
7 Records and close-outThe full record set and as-built drawings to Network Rail within six weeks, the monitoring record, the Health and Safety FileEverything above, closed out and on recordNothing, you receive it

Network Rail’s standard covers open-cut crossings as well as trenchless ones. Everything below is the standard read for a trenchless crossing, a directional drill or a rammed casing, with the open-cut content left out. Where a stage names a clause, that is where it comes from in NR/L2/CIV/044.

Stage 0

Before the first submission

More is set up before the first form goes in on a railway than on a road, and the earlier it is done the less it holds up the job. Five things.

  • Asset Protection. Network Rail have a team whose job is to protect the railway when anyone else works on or near it, and every crossing goes through them. They are engaged first, and they tell you which route the job is on. A crossing for a developer or a utility is what Network Rail call an Outside Party job.
  • The agreement. An asset protection agreement is put in place between Network Rail and the scheme owner. For a routine utility crossing that is usually a Basic Asset Protection Agreement, a BAPA. It lets Network Rail oversee the work and be paid their costs, and it commits the scheme owner to controlling ground movement, working under Network Rail’s access rules and handing over the design certificates. We deliver the crossing under it. Under the agreement, method statements go to Network Rail at least 20 working days before the works and nothing starts without their written acceptance.
  • The wayleave. Having a pipe under Network Rail’s land needs a legal permission, a wayleave or an easement. The scheme owner applies for it, after talking to Asset Protection and before the Approval in Principle goes in (clause 7.1). It has its own lead time.
  • The roles. Network Rail want to know who is who and see it on a project organisation chart, the scheme owner and their representative, the Principal Designer, the Principal Contractor, us as the specialist trenchless subcontractor, the monitoring contractor, the contractor’s engineering manager and responsible engineers (formal roles Network Rail require on any work touching the railway), who would fix a track defect if one arose, and how their Track Maintenance Engineer is kept informed. They ask for CVs, and they want to see recent experience of the same kind of crossing in the same kind of ground. Ours goes in.
  • The checker. Every crossing design is independently checked, and how independent is set by a design check category. A crossing for an Outside Party is normally Category 3, which means the check is done by a company that is a separate legal entity from the designer. The scheme owner allocates the category and appoints the checker, with Network Rail’s acceptance obtained before the appointment is made. We propose a checker we have worked with, put the acceptance in, and commission the check.

One more that is easy to miss. Network Rail want every existing service near the crossing found before anything is dug, and that includes the boreholes. So the records search begins here, not when the rig arrives.

What we need from you

  • Where the crossing is. A plan, a drawing or a grid reference is enough to start. If Network Rail have already given you a reference for the scheme, or a line name and a mileage, send that too, but do not worry if you have never spoken to them.
  • What is being installed. The service (water, gas, power, telecoms, drainage), the size and material of the pipe or duct if you know it, and how many. If you only know the cable or pipe that has to get across, we can size the duct for it.
  • Who owns the scheme. Network Rail deal with the party the crossing is for, so we need to know whether that is you or a utility company you are working for, because that party signs the agreement and applies for the permission to be under the railway.
  • Land either side. The rig sits on one side of the railway and the pipe comes out on the other, both outside Network Rail’s fence, so we need to know whose land that is and that we can get onto it.
  • Your dates. When you would like it in the ground, so we can tell you honestly whether the approvals will allow it.
Where the site information goesThe utility records search starts now. Network Rail want every existing service near the crossing found before anything is dug, and that includes the boreholes, so the records are asked for on day one rather than when the rig arrives.
What we need from youWhere the crossing is, what is being installed, who the scheme owner is, whose land sits either side of the railway, and when you would like it in the ground. Each one is explained in this section.
ThenAsset Protection engaged, the agreement in place, the wayleave applied for, the roles named and the independent checker accepted. The first submission can be written.

Stage 1

Approval in Principle (FORMA)

The Approval in Principle, the AiP, is the opening submission. It is Network Rail agreeing the basis of the design before the detailed design is done, on their FORMA certificate (Form 001 on older jobs). It carries more than its name suggests, because Network Rail want the whole shape of the job, the constraints, the desk study, the method, the risks and a first pass at the numbers, in front of them before anything is fixed.

What goes in it (clauses 7.2 to 7.4, 12.2, 12.5, 12.6, 12.10 and Appendix A)

  • The site constraints. Rivers, buildings and services near the crossing, the ground including any landfill or old mining, third-party restrictions, the working area, programme restrictions, how the crossing ties into existing assets, the alternatives considered, and the environmental picture.
  • The desk study. The general topography, the local geology, historical boreholes reviewed for what they say about the ground and the groundwater, previous land use and any sources of contamination, an outline of the scheme and its construction risks, and what ground investigation the desk study says is needed.
  • The utility records. A full search with the statutory undertakers for records of their services, a request to Network Rail’s records department for their own buried services, and a request to Network Rail’s drainage engineer for the track drainage. Everything found goes on the drawings.
  • The method. The trenchless method proposed and why it was chosen, the other methods considered and why they were rejected, and how the crossing will be kept within Network Rail’s rules.
  • The crossing itself. The horizontal and vertical alignment with the launch and reception pits, a cross section, an outline geological long section, and how the crossing will be reached, inspected and maintained in future.
  • The risks. The hazards for design, construction, maintenance and eventual removal, considered with the Principal Designer, and the Designer’s Risk Assessment. The contingency plan is submitted with the AiP too, covering the things that could go wrong that can be recovered from.
  • Preliminary calculations and drawings. A first settlement assessment, a first heave assessment and a first pipe loading check, marked preliminary, with the site plan, the long section with the geological profile and the pit arrangements. The final versions come with the design.
  • The paperwork about the people. The project organisation chart, the appointments with CVs, the wayleave application, and a schedule of the records that will be kept on site.
  • The monitoring approach. How the volume of spoil and drilling fluid will be measured against progress, which becomes the works monitoring plan later.

It is at this review that Network Rail’s Track Maintenance Engineer advises what movement the track can tolerate. The standard’s figure is 5mm of settlement or heave at track level, and on constrained track it can be less. A fully endorsed AiP is valid for three years provided construction starts within that time.

What we need from you

  • Your sign-off on the line and on what is going in it, because the AiP fixes the basis of the design and changing either later means going round again.
  • Anything you already hold on the site. A topographical survey, any ground investigation or borehole logs, drawings of existing services, previous letters or emails with Network Rail. It saves repeating work and it goes in as existing information.
  • The wayleave or easement application put in with Network Rail. We tell you what to send and when, but it goes in your name.
  • The asset protection agreement signed, or at least in hand, because Network Rail will not take the job forward without it.
  • Your say-so on the independent checker we propose, because you as the applicant appoint them, with Network Rail’s acceptance.
Where the site information goesThe utility records search, gathered from the utility companies, from Network Rail’s own records and from their drainage engineer, and any ground investigation, borehole logs or surveys that already exist on or near the line. If site-specific boreholes have already been put down, the AiP is supported by them. If not, they follow it, which is the usual case.
What we need from youYour sign-off on the line and on what is going in it, anything you already hold on the site, the wayleave application put in, the agreement signed or in hand, and your say-so on the checker we propose.
ThenNetwork Rail review it and send back their comments, we answer them, and the FORMA is endorsed. It stays valid for three years provided construction starts within that time. On to the ground.

Stage 2

Ground investigation and the baseline survey

This is the site work between the AiP and the design, and there are two halves to it. The ground investigation tells the design what the ground is. The baseline survey records what the track and the land look like before anything is done, so that anything that moves later can be measured.

The ground investigation (clause 8.3.3)

Network Rail’s standard requires the design of a trenchless crossing to be based on a ground investigation, done to the British Standard for site investigation and Eurocode 7, and it sets the minimum. Two exploratory holes, one on each side of the crossing, no further than 20m from the railway boundary, as close to the line of the crossing as possible without being on it, taken down below the lowest part of the crossing, with laboratory testing to confirm the soil properties, groundwater monitoring, gas monitoring and contamination testing. If the two holes disagree with each other, more investigation is needed before the works can go ahead. Where the ground is soft enough we dig trial pits ourselves. The boreholes and the laboratory testing we arrange through specialist ground investigation firms, specifying the tests that matter for a bore, and we interpret the results for the crossing. The results are written up in a ground investigation report and feed a ground model with a geological long section showing the groundwater.

The baseline survey (clause 7.5.2)

After the AiP has gone in and before the design and check certificate, a baseline survey is carried out. It covers the railway lines and the infrastructure around them, any embankment or cutting, the general topography (this is where the topographical survey along the line goes), and a look at any existing surface abnormalities along the line of the crossing outside the railway fence. It includes a dilapidation survey, a record of the condition of every Network Rail asset near the crossing, so nobody can later argue about what was already there. The survey targets that the track monitoring will read are set at the same time and their starting positions recorded. If a long time passes between the survey and the works, it might need to be repeated and the targets cleaned and reset, because maintenance on the line can invalidate it.

The work on the track itself is arranged with Network Rail through Asset Protection. It can need a short closure of the line, which Network Rail schedule, and the standard says to allow for that in the programme.

What we need from you

  • Access to the land on each side of the railway for the drilling rig that puts the boreholes down. The holes sit close to the crossing line and within 20m of Network Rail’s fence, which almost always means on your side of it, on the same ground the pits will use.
  • Your decision on any investigation beyond the minimum, if we recommend it, with the reasons in front of you. The minimum of two holes is Network Rail’s requirement, so that part is not optional.
  • The survey work on the track itself, the baseline and setting the monitoring targets, is arranged with Network Rail through Asset Protection. You do not organise it yourself, but it is done in your name under the agreement, and it can need a short closure of the line, which Network Rail schedule.
Where the site information goesThe boreholes and the laboratory results, the topographical survey along the line, and the track baseline and dilapidation record. Everything the design will be built on and everything the works will be measured against.
What we need from youAccess to the land on each side of the railway for the borehole rig, your decision on any investigation beyond the minimum two holes, and the track survey arranged in your name through Asset Protection.
ThenThe ground model is built and the design is done against it. Allow time for the laboratory testing, because the settlement calculation cannot be finished without the results.

Stage 3

The design

The design is the crossing as it will be built and the proof that it will behave, and it is what the independent checker and Network Rail will read most closely. On older jobs its basis went in on a Statement of Design Intent, Form 002. On the current lettered forms that content rides inside the FORMA and FORMB package, and Network Rail’s Asset Protection engineer confirms what they want on your job.

What goes in it (clauses 8, 10, 12.3 and 12.9, Appendix B)

  • The ground. A summary of the ground investigation with the ground model and the geological long section, and the ground investigation and geotechnical design reports themselves, both issued in final with the certificate.
  • The methodology and the loads. How the permanent crossing and the temporary works are designed, and the loads on the crossing, the ground and cover above it and the live load of rail traffic, taken from the recognised rail load model and spread down through the cover to the pipe.
  • Settlement and heave. An assessment of the ground movement the crossing will cause at track level, against the 5mm limit or the tighter figure the Track Maintenance Engineer gave. The standard says how to do it. In soft ground the settlement trough over the bore is calculated by the recognised trough methods, and where there is more than one bore the troughs are added together. In rock the movement is assessed from the closure of the bore. Heave, the ground being pushed up rather than settling, is assessed against the same limit.
  • The pipe. The structural check on the carrier pipe or casing in the ground, how much it will flatten under load and whether it could buckle, each with a margin.
  • The pits, the bore and the fluid. The launch and reception pits and their support, the stability of the bore face, and the drilling fluid mix and how the risk of it breaking out to the surface is controlled.
  • The Track Monitoring Plan and the Works Monitoring Plan. The targets on the track and how often they are read, the stepped trigger levels set around the predicted movement with an action against each, and the wider monitoring of the ground on the approach, groundwater, vibration if relevant, and the spoil and drilling fluid measured against progress. The Track Monitoring Plan is written to Network Rail’s own monitoring standard and is what the survey company works to.
  • The plans for when things go wrong. The contingency plan developed from the AiP, and an emergency plan for the things that cannot be recovered from, each with the trigger events Network Rail list and the actions and the named people against them.
  • The drawings and the risk assessment. The final drawings, and the Designer’s Risk Assessment updated.

Where the site information goes

The utility survey on the ground goes in here, the located services plotted onto the drawings with the clearance to each. The calculations, the drawings and the monitoring plan all attach. Because we design and install, the method and the monitoring thresholds in the design are ones we know can be achieved on site.

What we need from you

  • Confirmation of the final pipe or duct requirements, because the structural check is done on the actual pipe, not a placeholder.
  • Agreement on where the pits sit and whose land they are on, because the drawings fix them.
  • Answers to anything Network Rail’s reviewers direct at the scheme owner rather than at the designer, which we help you draft.
Where the site information goesThe utility survey on the ground plotted onto the drawings with the clearance to each service, the settlement, heave and pipe loading calculations, the drawings, and the track monitoring plan the survey company will work to.
What we need from youThe final pipe or duct requirements confirmed, agreement on where the pits sit, and answers to anything Network Rail direct at the scheme owner.
ThenThe design goes to the independent checker with the reports and the calculations behind it.

Stage 4

The independent check and the design and check certificate (FORMB)

The finished design goes to the independent checker, and the result is the design and check certificate, Network Rail’s FORMB (Form 003 on older jobs). This is the stage most often misunderstood on a rail crossing, so it is worth being clear about who does what.

  • The check. For an Outside Party crossing the design check is normally Category 3, which means it is done by a company that is a separate legal entity from the designer, appointed with Network Rail’s prior acceptance. The checker does their own settlement and pipe calculations, by a different method where the design is novel, and confirms the design meets the standard. We commission this check alongside our own design.
  • The certificate for the crossing. The FORMB certifies the permanent works, the bore or casing and the ducts or pipe left in the ground, and there is almost always one. The ground investigation and design reports are issued in final with it.
  • The certificate for the temporary works. A FORMC is needed only where the temporary engineering near the track puts the railway at risk, a deep thrust pit right by the line, sheet piling, or anything that supports the track. On a typical directional drilling crossing with the pits set well back from the railway there is usually only a FORMB, and the pits are handled as ordinary temporary works under our own procedures.
  • The certification of the check. Network Rail’s standard requires the settlement and heave assessment, the drilling fluid design, any dewatering and any temporary ground support to be checked at this stage, and the certificate records that they were.

Network Rail then review the certificate and accept it. It is worth repeating that they do not do the check. It is two opinions on the design, ours and the checker’s, and Network Rail confirm the process was followed. Once accepted, the construction drawings are stamped Approved for Construction and the calculations marked final.

What we need from you

  • Usually nothing new. We commission the independent check, and the certificates come to you as the applicant to pass to Network Rail through Asset Protection, or we submit them for you through the same route, whichever the agreement says. Either way it is your name on the application.
Where the site information goesNothing new. Everything above is now certified, and the ground investigation and design reports are issued in final with the certificate.
What we need from youUsually nothing new. The certificates go to Network Rail in your name as the applicant, through Asset Protection.
ThenNetwork Rail review and accept the certificate. The construction drawings are stamped Approved for Construction, and the works can be planned.

Stage 5

Before site

Between the certificate and the rig arriving there is a set of things Network Rail need in hand, and a set of dates that only Network Rail can give.

  • The method statements. Under the agreement, the risk assessments and method statements go to Network Rail’s contact at least 20 working days before the works, and nothing starts without their written acceptance. That acceptance is asset protection only, it is not approval of the design, which is what the certificate was for. Our RAMS carry the construction risks, the controls, and how the designer’s residual risks are managed on site.
  • The monitoring plans accepted. The Track Monitoring Plan and the Works Monitoring Plan agreed with Network Rail, and the survey company or the employer’s engineers ready to read them.
  • The construction drawings and the plans. The Approved for Construction drawings and calculations, the contingency and emergency plans in their final form with the trigger values and the named people, and the inspection and test plan setting out the records that will be kept.
  • The targets. The survey targets on the track checked, cleaned or reset if time has passed since the baseline, and their advance readings taken and given to Network Rail to review.
  • Access. The line normally stays open while we drill, and we prefer to work that way where we can. In some cases Network Rail, the employer or the client will want the drilling done in a possession, a booked closure of the line, and that is booked through Network Rail well ahead of the works. Any short line closure needed for the survey work is scheduled the same way.
  • The people. The contractor’s engineering manager and responsible engineers in place, and Network Rail’s site contact known to the crew.

What we need from you

  • The asset protection agreement in force and the wayleave granted, because Network Rail will not accept the method statements without them.
  • A named person on your side who receives the monitoring readings and can make a decision if a trigger level is reached.
  • If Network Rail, the employer or you want the drilling done in a possession (a booked closure of the line), that is booked through Network Rail well ahead and we programme around it.
Where the site information goesNothing new. The plans and method statements written earlier are finalised and accepted, and the monitoring targets on the track are checked, cleaned or reset if time has passed since they were put in.
What we need from youThe agreement in force and the wayleave granted, a named person on your side for the monitoring readings, and any possession booked well ahead if one is wanted.
ThenRig on site.

Stage 6

The works, with the track monitored

This is the stage all the approvals were for. The design said how much the track would move. The works prove it, reading by reading, with the line open above.

What happens (clauses 13.2 to 13.4 and 14)

  • The baseline. The survey targets read before the drill starts, which every later reading is compared against.
  • Monitoring on the approach. Monitoring points are set between the launch pit and the railway boundary, and between the boundary and the track, and read as the bore approaches, so any movement shows before the bore is under the railway. The engineers on the design, construction and monitoring side and Network Rail’s project engineer review those results before the bore is allowed to continue under the track.
  • The pilot bore. The pilot hole, the first small-diameter pass that sets the line and level of the crossing, is tracked from ground level with a guidance system Network Rail have approved, and its as-built line and level are accepted by Network Rail before the bore is opened out to size. The tolerance for a directional drill is one metre either way on line and level, and if that is not achieved a post-installation statement records the departure and confirms there is no risk to the railway.
  • The track read through the drill. The targets on the rails read at the frequency in the Track Monitoring Plan and checked against the stepped trigger levels, with the actions in the plan followed if a step is reached, and the readings passed to you and to Network Rail as the job runs.
  • Spoil and fluid reconciled. The volume of drilling fluid used is reconciled against the size of the bore every shift, because fluid or ground going missing is the early sign of a void forming under the track. If the numbers do not add up the work stops until the ground around the bore and the track above have been confirmed stable.
  • The routine under railway land. Once the bore is under Network Rail’s land the standard requires round-the-clock working until it reaches the reception pit and the pipe under the railway is grouted tight, so the time in which ground could be lost is as short as possible. There is a review meeting each day on the settlement readings and the spoil reconciliation, and a formal end-of-shift handover report every shift.
  • Monitoring after. The track continues to be read for the agreed period after the pipe is in, because ground movement can lag the works.
  • The as-built. The installed line and level surveyed and recorded, with the records Network Rail list kept as the job goes, dates and shifts, stoppages, ground and groundwater met, pull loads against progress, and photographs.

The track monitoring is carried out by a specialist survey company or by the employer’s engineers, never by the drilling crew, and always to the accepted Track Monitoring Plan. We plan the works around it and stop when it says stop. On a Network Rail crossing it is the track that is watched, targets on the rails and on the structures beside them, so it is track monitoring rather than the surface monitoring of a road crossing, though it is looking for the same things, settlement, heave and any other ground movement.

What we need from you

  • Access to the pits and the compound each day.
  • Your named contact available while we are under the railway, because the readings come to you as the job runs and a decision might be needed quickly.
Where the site information goesEvery monitoring reading, the drilling records, the spoil and fluid reconciliation sheets, the pilot bore survey and the as-built survey of the installed line and levels.
What we need from youAccess to the pits and the compound each day, and your named contact available while we are under the railway.
ThenPipe in, monitoring run to the agreed end, records collated. The last stage closes it out.

Stage 7

Records and close-out

The last stage is the record. Network Rail’s standard says a full set of record information, including the as-constructed drawings, is issued to Network Rail Asset Protection within six weeks of finishing on site, and the schedule of what is kept was agreed back at the AiP.

What goes in it (clause 14.2 and Appendix A)

  • The crossing as built. A description of the works, the track mileage, the excavated bore diameter, the internal and external diameter of the pipe, the pipe material with its data sheets, the joint type, the length installed, and the final line and level achieved.
  • The record of the drilling. The date, start and finish of every shift and any stoppages, the survey checks carried out, the soil and groundwater met, any groundwater control used, the spoil and drilling fluid reconciliation with the volumes used, and the pulling loads against progress.
  • The monitoring record. Every track reading against the trigger levels, from the baseline to the end of the agreed period after, and any action taken.
  • Compliance and drawings. The material compliance certificates, the as-built record drawings, and a post-installation statement if a tolerance was missed.
  • The plans for the future. The asset management plan for the crossing that Network Rail’s standard asks for, and the Health and Safety File information under CDM 2015, which is what protects the next person to work near it.

Network Rail then check the crossing is recorded on their digital asset database, if their system is available for it, so it can be found by anyone planning work on that stretch of line in future.

What we need from you

  • Nothing. You receive the record set and it goes into your Health and Safety File. Where the crossing is being handed to a utility company, they get their copy too.
Where the site information goesEverything above, closed out and on Network Rail’s record.
What we need from youNothing. You receive the record set for your Health and Safety File.
ThenThe crossing is complete on Network Rail’s record and, if their system is available, on their digital asset database, so the next person to dig near the railway can find it.

Three things that sit alongside the sequence

The forms, lettered and numbered

The certificates that carry a crossing through approval belong to NR/L2/CIV/003, and they have been renamed over the years, which causes real confusion in old paperwork. The current forms are lettered. FORMA is the Certificate of Approval in Principle, FORMB the Certificate of Design and Check for the permanent works, FORMC the same for temporary works. Earlier issues numbered them, Form 001 for the Approval in Principle, Form 002 for the Statement of Design Intent and Form 003 for the design and check certificate, and both generations turn up in our own completed jobs. One thing to keep separate. Network Rail also publish standard drawings for open-cut crossings called NR/CIV/SD/FORMA/610 and FORMB/610, and they are drawings, not these certificates.

A big crossing is a structure

A crossing with an internal diameter over 2.0m is managed as a structure on top of the UTX process, which pulls in the full Network Rail structures regime. A normal utility crossing sits well under that size.

National Highways and Network Rail together

Where a route crosses both a National Highways road and a railway, both processes run, each with its own authority, its own submissions and its own monitoring. Our CD 622 guide walks through the road side the same way this page walks through the rail side. A river or a canal on the same route is its own regime again, walked through in our FRA3 river crossing guide and our canal crossing guide.

How long it takes

Months, not weeks, and most of the time goes at the front end. Network Rail’s standard does not give an overall figure, but the pieces add up. Asset Protection has to be engaged and the agreement and the wayleave put in place before the first submission. The Approval in Principle is reviewed and commented on before it is endorsed. The ground investigation has its own lead time and the laboratory testing has another before the design can be finished. The independent checker needs time with the design. The method statements go in at least 20 working days before the works and any possession or line closure is booked well ahead of that. Then the records within six weeks at the end.

The things that shorten it are all at the front. Engaging Asset Protection straight away, getting the agreement and the wayleave application moving in parallel with the AiP rather than after it, sending us anything you already hold on the site, and lining up the checker early. The stages run in sequence, so any delay early on pushes the end date back by the same amount.

What you end up holding

  • The endorsed FORMA, the Approval in Principle
  • The FORMB (and FORMC if there was one) with the independent Category 3 check behind it
  • The ground investigation and design reports, the drawings and the settlement, heave and pipe loading calculations
  • The Track Monitoring Plan, the Works Monitoring Plan and the contingency and emergency plans
  • The baseline and dilapidation survey and every track reading from the works
  • The drilling records with the spoil and fluid reconciliation, and the as-built drawings with the final line and level
  • Network Rail’s acceptance on record and the crossing on their asset database
  • The Health and Safety File information for the crossing

Questions answered

Network Rail UTX stage questions

Do I have to sign something with Network Rail?

Yes. A crossing under the railway is third-party work on an operating line, so Network Rail oversee it through their Asset Protection team under an asset protection agreement. For a routine utility crossing that is usually a Basic Asset Protection Agreement, a BAPA, on what Network Rail call the Outside Party route (an Outside Party is anyone working near the railway who is not Network Rail or a contractor working for them). It is signed by the scheme owner, the client or the utility whose service it is, and we deliver the crossing under them. It commits the scheme owner to controlling ground movement, working under Network Rail's access rules, paying Network Rail's costs and handing over the design certificates. Separately, the scheme owner applies for a wayleave or easement, the legal permission to have the pipe under Network Rail's land, and that application goes in before the Approval in Principle. We tell you what to send and when.

Are boreholes optional under a railway?

No. Network Rail's standard requires the design of a trenchless crossing to be based on a ground investigation, and it sets a minimum, two exploratory holes, one on each side of the crossing, within 20m of the railway boundary, as close to the line of the crossing as possible without being on it, and taken down below the lowest part of the crossing, with laboratory testing, groundwater, gas and contamination checks. If the two holes disagree with each other, more investigation is needed before the works can go ahead. That is a real difference from a National Highways crossing, where the number of boreholes is a decision. We dig trial pits ourselves where the ground is soft enough and arrange the boreholes and laboratory testing through specialist ground investigation firms, then interpret the results for the bore.

Where does the utility survey go?

In two places. The records search comes first and goes into the Approval in Principle. Network Rail's standard asks for a full utility search with the statutory undertakers (the water, gas, power and telecoms companies), a request to Network Rail's own records department for their buried services, and a request to Network Rail's drainage engineer for the track drainage, and every service found goes on the drawings. The survey on the ground, the electromagnetic and ground-penetrating radar locate along the line with covers lifted to read depths, feeds the design and goes onto the design drawings with the clearance to each service. When the crew arrive they sweep the line again before breaking ground and prove anything critical by hand.

Who does the track monitoring, and does the line have to close?

The track monitoring is carried out by a specialist survey company or by the employer's engineers, never by the drilling crew, and always to a Track Monitoring Plan agreed with Network Rail. Survey targets are fixed to the rails and to any nearby structures, a baseline is read before the works, and the track is read on the approach, through the drill and for an agreed period after, against stepped trigger levels with an action written against each. The readings are reviewed by the engineers before the bore is allowed under the railway, and they come to you and to Network Rail as the job runs. The line normally stays open while we drill, that is what the monitoring is for, and we prefer to work without a possession where we can, but in some cases Network Rail, the employer or the client will insist on one, and setting the targets on the track can need a short closure of the line, which Network Rail schedule.

What are FORMA, FORMB and FORMC, and the Form 001, 002 and 003 I see in old paperwork?

They are the certificates in Network Rail's engineering assurance standard, NR/L2/CIV/003, that carry a crossing through approval. FORMA is the Certificate of Approval in Principle, Network Rail agreeing the basis of the design before the detailed design is done. FORMB is the Certificate of Design and Check for the permanent works, the crossing that stays in the ground, and there is almost always one. FORMC is the same for temporary works, needed only where the temporary engineering near the track, a deep thrust pit or sheet piling say, puts the railway at risk. Earlier issues of the standard numbered the same forms, Form 001 for the Approval in Principle, Form 002 for the Statement of Design Intent and Form 003 for the design and check certificate, and both generations turn up in our own completed jobs. On the current lettered forms the design intent rides inside the FORMA and FORMB package rather than as a separate certificate. Network Rail's Asset Protection engineer confirms which forms apply on your job, and we submit on whichever they ask for.

What happens if a trigger level is reached?

The Track Monitoring Plan sets stepped trigger levels around the movement the design predicts, with an action against each step, and the contingency and emergency plans say who does what and how quickly. At the lower steps that means more frequent readings and a review of the drilling parameters. At the top it means stopping the works, and Network Rail can step in and take protective measures on the track themselves if they judge the railway is at risk. The plans also cover the other events Network Rail want covered, unexpected ground or water, drilling fluid going missing, spoil that does not match progress, and a hole appearing at the surface. Because the line is normally open, movement is being watched with trains running over it, which is why the readings are reviewed before the bore goes under and why the reconciliation of spoil and fluid is done every shift.

What do I get at the end, and how quickly?

The full record set and the as-built drawings go to Network Rail Asset Protection within six weeks of finishing on site, and you hold the same. That is the endorsed FORMA, the FORMB (and FORMC if there was one) with the independent check, the ground investigation and design reports, the drawings and calculations, the monitoring plans, the baseline and every monitoring reading, the drilling records with the spoil and fluid reconciliation, the material certificates, the final line and level, and the as-built drawings for your Health and Safety File. If a tolerance was missed on site, a post-installation statement goes with it recording the departure and confirming there is no risk to the railway. Network Rail then check the crossing is on their digital asset database.

Is HS1 different?

Yes. High Speed 1, the line from London St Pancras to the Channel Tunnel, is looked after by Network Rail (High Speed) under its own Asset Protection handbook, and it is stricter. Undertrack crossings shallower than 4.8m are not permitted there, and it runs its own set of forms. The shape of the process, agreement, approval in principle, independent check, monitored works, records, is the same, but the figures and the paperwork are not, so if your crossing is under HS1 tell us at the start.

Planning a crossing under the railway?

Send us the line, the service and where the pits can go, and we will tell you which stages your crossing needs, what we already hold, and what we need from you.