A selection of real under-track crossings. We've also installed four-way 180mm UTX bundles for BAM and Western Power, multiple rail crossings for HVMS, and 355mm Network Rail culvert relining.
Tonteg rail scheme, South Wales
Balfour Beatty / Transport for Wales · 2022
6 × 4-way 180mm UTX · 24 ducts · tight-radius design
Six four-way under-track crossings, 24 ducts in total, installed for the Transport for Wales rail scheme. The design was a complicated one: the bores had to be steered on a very tight radius to fit a very small working area, then threaded beneath the railway without disturbing the line above.
Horsham, West Sussex
KGJ Price · 2022
2 × 4-way 160mm HDPE · 50m each · 7m apart · through rock
Two under-track crossings beneath the Network Rail line at Horsham, each carrying four 160mm HDPE ducts, eight in total, with the bores held 7m apart. Each 50m bore was steered on a curve through clay into mudstone and sandstone, with the full Network Rail approval: design to NR/L2/CIV/044 and the NR/L2/CIV/003 Approval in Principle and design and check certificates.
Newton Aycliffe
Story Rail
8 bores · 180mm to 500mm dia · within an overbridge easement
A run of eight trenchless installations from 180mm ducts up to 500mm drainage, all drilled under the line of an existing overbridge so every bore stayed within the bridge footprint for the land-ownership easement. Fitting eight bores into that width without them clashing made it one of our more involved rail jobs, delivered alongside Story Rail in the North East.
Royston Underpass, Hertfordshire
Birse Rail
4 × 225mm electric + 1 × 250mm gas · 150–170m bores · through chalk
Five separate crossings at Green Street, Royston: four 225mm electric ducts (33kV, 11kV and pilot cable) and a 250mm gas main, each drilled through chalk on a 150m to 170m bore. Every bore had to stay within a tight easement under a proposed railway underpass, and sit below its dig level, so the services could be diverted before the underpass was excavated. We deliberately kept the bores small relative to the pipe, 225mm pipe in a 270mm bore, to hold the ground movement well under Network Rail's 5mm settlement limit, coming out under 1mm on every bore.
Broomloan Rail Depot, Glasgow
George Leslie Ltd
Glasgow Subway (SPT) · 3 × 3-way 160mm · 140m each · live rails + active subway
Three pipelines drilled across the live rails and the active Glasgow Subway at the SPT Broomloan depot, taken down to 10m below rig level to hold around 3m of cover beneath the running subway. Through shocking weather and a mud-bath site, all three were completed in three days, against the three weeks the contractor had allowed.
Ford Quarry, Sunderland
Esh / Sunderland City Council · 2020
80m · 180mm drainage · through rock
An 80m, 180mm drainage under-track crossing at Ford Quarry, steered through rock, including the full Network Rail consultation and approval to NR/L2/CIV/044. Delivered for Esh as principal contractor, with Sunderland City Council the client.
Southend Airport rail terminal
Birse Rail
180mm drainage · ~42m · across live Network Rail track
A 180mm drainage UTX drilled to a ~1% fall straight across live Network Rail tracks at the new airport terminal, through sand, gravel and clay, and completed inside a single nightshift.