Skip to content
The tidal River Parrett at Pawlett Hams, with the S.W.Directional Drilling setting-out underway on the bank

Case Study · River Crossing

A water main drilled under the tidal River Parrett

At Pawlett Hams near Bridgwater, we drilled a 252 metre water main clean under the tidal River Parrett, through clay and rock, to restore freshwater to a rare Somerset grazing marsh. One of the longest river crossings drilled in the South West, delivered in about four days with no impact to the river.

  • 252m crossing
  • 355mm water main
  • Tidal river, clay & rock
  • Completed 2017

The job

Getting fresh water back to the Hams

Pawlett Hams is a stretch of rare coastal grazing marsh on the Somerset Levels, laced with the drainage ditches that keep it healthy. The job came down to a simple problem. The ditch on the far side of the River Parrett had water, the ditch on the Hams side had run dry, and the old ductile-iron main that linked the two across the river had been destroyed by high tides in 2015. With it gone, the marsh was left dangerously short of water for its grazing cattle and its wildlife. The Parrett Drainage Board needed a new pipe across the river that would actually last.

The catch is the river. The Parrett here is a wide, tidal, salt-water estuary, and the land each side is protected marsh. Digging a trench across it, or hanging a pipe off a bridge, was never on. So the Board and their consultant engineer, Clive Onions, brought us in to drill it. We worked up the crossing design with Clive, then delivered the work for the Board.

The answer was to steer a new main several metres below the riverbed, from a pit on one bank to a pit on the other, leaving the river and the marsh untouched.

The S.W.Directional Drilling crew with the Ditch Witch rig at the completed Pawlett Hams crossing, the reamer sitting in the drilling fluid in the pit
The reamer sits in the pit in the drilling fluid that covers the pipe just pulled through, with the drill rods stacked by the rig. Other than putting the machine away, the job was successfully completed. The two men on the right are from the Somerset Drainage Board, the client, and you can tell from their faces they were happy with it. (From the Somerset Drainage Boards Consortium press release.)

Project at a glance

Worked forThe Parrett Drainage Board (Somerset Drainage Boards Consortium)
Consultant engineerClive Onions, who we developed the crossing design with
LocationPawlett Hams, near Combwich and Bridgwater, Somerset
CrossingUnder the tidal River Parrett, bank to bank
Pipe252m of 355mm HDPE water main, supplied, butt-fusion welded and de-beaded
BoreSingle pilot bore reamed to ~530mm, with a launch and reception pit, one on each bank
GroundworksWe excavated the launch and reception pits on each bank and managed the drilling spoil ourselves
DepthAround 5m beneath the riverbed at the lowest point
GroundA mixture of clay and rock, under a tidal estuary
ProgrammePilot bore started Tue 1 Aug, pipe installed by Fri 4 Aug 2017 (about four days)
PurposeReplaced a water main destroyed by high tides in 2015, restoring freshwater to the grazing marsh
SettingPawlett Hams: 397ha of rare coastal grazing marsh, part of the Bridgwater Bay SSSI
OutcomeCompleted on budget, one of the longest river crossings drilled in the South West

Our general arrangement, designed and checked in-house.

The crossing

252 metres, bank to bank

We installed 252 metres of 355mm HDPE water main under the river in a single continuous length. The pipe was supplied, butt-fusion welded into one string on the bank and de-beaded, taking the internal weld bead back out of each joint so the bore stays clean and the main can be pressure-cleaned with a foam pig in years to come.

The crossing did not start out this way. The original design ran the whole route as one longer bore. We reworked it into two shorter drills between the same start and end points. One is this bore under the river, the other a drill across the field beyond it that made up the rest. Keeping each individual crossing shorter takes risk out of the job and usually keeps the cost down too, so two shorter, well-controlled bores often beat one long pull, especially on a job that matters this much.

The pilot bore was steered from a launch pit on one bank, dipping down to around 5 metres beneath the riverbed at its lowest, then back up to a reception pit on the far bank. It ran through a mixture of clay and rock, the kind of mixed ground that decides which tooling you reach for. We then reamed the bore out to about 530mm and pulled the welded main through.

The groundwork on each bank was ours too. We excavated the launch and reception pits on both sides of the river and managed the drilling spoil ourselves, working the sites between the tides on the soft ground of the Hams.

How we guided it is the part most people find surprising. Rather than an expensive downhole wireline or gyro system, we steered the bore with a DigiTrak F5+ walkover locator in Drill-To mode. The crossing was longer than that kit is really meant to reach, so at low tide we worked a small boat out onto the mud flats on each bank to pick the signal up from out over the water, held the depth we needed, and let the middle section run unguided across the river. Left-to-right accuracy matters little mid-river, so that was a sensible trade, and the gentle curve on the as-built line is the result of guiding it this way.

Bringing in a wireline or gyro guidance system would have cost around £20,000, for pinpoint accuracy this crossing simply did not need. Leaving it out saved the client that money outright. It is the sort of call that comes from having drilled a lot of rivers and knowing where the cost is worth paying and where it is not.

From start to finish, the pilot bore began on the Tuesday and the pipe was in by the Friday, about four days on a crossing most people assume would take weeks. At no point did anything go into the river. No cofferdam, no dredging, no in-channel works, which is exactly what a site like this needs.

S.W.Directional Drilling original long-section drawing for the Pawlett Hams crossing, showing the single bore dropping beneath the River Parrett and rising to the far bank
Our original long section for the crossing, the bore dropping beneath the river and climbing to the far bank. This was the first revision, drawn as a longer bore. We then split the route into the two shorter drills described above. A shorter individual crossing carries less risk and usually costs less, so two shorter bores often beat one long one. That dip under the riverbed is what keeps the main clear of the tides.
S.W.Directional Drilling site layout for the Pawlett Hams crossing, showing the River Parrett, the pilot bore line, the mud banks and the launch and reception areas
Our as-built site layout, recording the line as drilled. The route followed the client's own crossing drawing, running across the River Parrett between the launch and reception areas, threaded between the mud banks, sluices and rhynes of the Hams. The slight curve is the path we actually steered from the mud flats.

Why it mattered

A protected marsh, and a 50-year supply

Pawlett Hams is not ordinary farmland. It is 397 hectares of rare coastal grazing marsh and forms part of the Bridgwater Bay Site of Special Scientific Interest, notified at European and international level. Its network of wildlife-rich ditches and rhynes supports water voles, rare plants and insects, and the marsh is vital winter habitat for migratory birds such as curlew, shelduck, dunlin and redshank.

Fresh water keeps those ditches stock-proof and the habitat healthy, so getting the supply back mattered well beyond the farm gate. Because the new main sits several metres below the riverbed, out of reach of the tides and scour that destroyed the old one, the restored supply is expected to serve the area for at least the next 50 years. The river crossing was the headline, but not the whole job. Alongside it we drilled across the fields and installed around 200 metres of gravity drainage, tying the ditch network together and balancing the water levels between the ditches on each side.

The people closest to the site summed up why it was worth doing. Once complete, the project drew warm words from those responsible for the marsh.

"We are delighted to see the project completed. Once the pipeline delivers freshwater to the area, it should quickly make the ditches stock-proof. This will provide drinking water for grazing animals, as well as improved habitat for the plants and animals that live there."

Colin Leppard, Natural England adviser (Somerset Drainage Boards Consortium press release)
Ordnance Survey location map showing the water supply pipe crossing under the River Parrett at Pawlett Hams, near Bridgwater
Where it crosses. The main runs under the River Parrett at Pawlett Hams, about three miles from Bridgwater. (Location map from the Somerset Drainage Boards Consortium press release, © Crown copyright.)

The outcome

One of the South West's longest river crossings, drilled in four days

A 252 metre water main installed under a tidal river, through clay and rock, on budget and without a single works in the river or across the protected marsh. The Hams have their freshwater back, and a supply built to last half a century. It is the kind of crossing that looks impossible from the bank and turns out to be exactly what directional drilling is built for.

Questions answered

Questions about this project

Can you install a pipe under a river without disturbing it?

Yes, and that is exactly what directional drilling is for. At Pawlett Hams we drilled a 252m water main clean under the tidal River Parrett, around 5 metres beneath the riverbed, with a launch pit on one bank and a reception pit on the other. Nothing went in the river itself, no cofferdam, no dredging, no in-channel works. The riverbed, the banks and the tidal flow were left untouched while the pipe was steered through the ground underneath. That is a big part of why drilling suits river and estuary crossings, especially on protected sites.

How long a crossing can you drill under a river?

The Pawlett Hams crossing was 252m bank to bank, which made it one of the longest pipelines drilled under a river in the South West at the time. Length on its own is rarely the limit. What really decides a river crossing is the ground, the pipe diameter and the room to set out a launch and a reception pit on each bank. Send us the survey and we will tell you honestly whether your crossing can be drilled in one shot. See our horizontal directional drilling service for how a crossing like this is planned.

Can you drill through rock under a river?

Yes. The pilot bore at Pawlett Hams went through a mixture of clay and rock beneath the estuary. We steer through mixed and rock ground regularly, using tooling matched to the conditions rather than fluid-hungry mud motors. Where a crossing is in harder rock we have a dedicated approach for it, set out on our rock directional drilling page.

Do you work on environmentally sensitive and SSSI sites?

Yes. Pawlett Hams is 397 hectares of rare coastal grazing marsh and forms part of the Bridgwater Bay Site of Special Scientific Interest, a habitat for water voles, rare plants and large numbers of migratory water birds. Keeping the work to a single small pit on each bank, with no works in the river or across the marsh, is what made the crossing acceptable on a site like that. Trenchless methods are often the only way to get a service across protected ground without damaging it.

Why drill a new pipe rather than dig a trench or build a bridge for it?

On a tidal river that is wide, salty and protected, an open-cut trench or a pipe bridge was never realistic. The old pipe had already been destroyed by high tides. Drilling puts the new main several metres below the riverbed, out of reach of the same tides and scour, in a single continuous length with no joints under the river. It is the solution that lasts, which is why the new supply is expected to serve the area for at least the next 50 years.

Got a river or watercourse to cross?

Send us your survey and levels. If your crossing can be directional drilled, under a river, a road or protected ground, we'll tell you honestly, with the bore designed to last.